A summary of VBA prosecutions, show cause notices, notices of decision, permit levy audits, proactive inspections and plumbing activities for the week.
Investigations (Building)
Warning letters issued: 1
Number of referrals for potential prosecution: 1
Investigations (Plumbing)
Warning letters issued: 2
Complaints and Statutory Referrals
A builder received a warning letter for failing to install fire doors and other ESM as required
The relevant building surveyor received a warning for failing to install signage to fire safety doors prior to issuing occupancy permit.
A builder received a warning letter for appointing a private building surveyor when there was another private building surveyor appointed
The relevant building surveyor received a warning letter for failure to require protection works.
A property owner received a warning letter for failing to ensure a building permit was in place.
Practitioner Discipline
Notices of Decision issued: 1
Number of Show Case Notices: 2
Proactive Inspections
218 inspections across 28 municipalities
Building Orders for Minor Work issued: 7
Plumbing Audits
Audits: 108
Re-audits: 11
Inspections: 31
Re-inspections: 4
Statewide Cladding Audit
Inspections completed: 11
Buildings assessed by Advisory Reference Panels: 3
Of the buildings assessed by ARPs, two were rated as higher risk.