Investigations (Building)
- Prosecutions initiated: 2
Complaints and Statutory Referrals
- Three registered builders received warning letters for failing to call for mandatory inspections.
Practitioner Discipline
- Notices of Decision issued: 1
Proactive Inspections
- 113 inspections across 24 municipalities
- Building Orders for Minor Work issued: 2
Plumbing Audits
- Audits: 74
- Re-audits: 2
- Inspections: 8
- Re-inspections: 2
Statewide Cladding Audit
- Inspections completed: 1
- Buildings assessed by Advisory Reference Panels: 7
- Of the buildings assessed by ARPs, four were rated high risk and three were rated moderate.